Permit checklist builder

Permit desks reject on paperwork far more often than on plumbing. The scope decides which drawings and calculations they expect and which inspections you have to book, and both lists are predictable once you know the scope. Tick what the job is and take the printed list to the counter.

What the plan checker is actually looking for

On a residential plumbing permit the reviewer wants three things they can check against a table: sizes with the calculation behind them, vent arrangement with the trap arm lengths written on it, and materials named to a standard. A riser diagram with sizes and a fixture unit schedule answers most of the first two on one sheet.

What slows a review down is a drawing that shows intent without numbers. Put the fixture unit totals and the trap arm lengths on the face of the drawing and the questions stop.

Ask two questions at the counter

Which code edition is adopted, and is the fee valuation-based or per fixture. Those two answers change the submittal and the price, and both are free to ask.

Inspections are a sequence, not a list

Underground before backfill. Rough before anything is covered. Final before the fixtures are used. Cover work that has not been inspected and the remedy is to open it again at your cost — no jurisdiction accepts photographs in place of an inspection, and none of them make an exception because the drywall is already up.

Book the rough with slack in it. A failed rough that has to be re-inspected costs a day, and days on a plumbing rough are days the framer, the electrician and the drywall crew are all waiting.

Code notes

IPC Ch. 1 The administrative chapter is where permit requirements, exemptions and inspection authority live — and it is the chapter jurisdictions amend most heavily. Two towns on the same code edition can have completely different submittal requirements. Always confirm with the authority having jurisdiction (AHJ) before you print the drawings.